تعمل شركة SoilTech على تثبيت الطرق المستدامة
وفّر حل التثبيت المبتكر من MetaFLO وفورات أساسية في التكاليف ومكاسب إنتاجية وفوائد بيئية للحفاظ على مشروع طريق واسع النطاق في الموعد المحدد وفي حدود الميزانية.
Location
Hidrolândia, GO, Brazil
تحدي
Traditional subgrade regularization methods are resource-intensive, even when managing soils containing a mix of silt, clay, lateritic gravel, and quartz gravel. These methods often require large volumes of water, resulting in high operational costs and prolonged completion times. To address these challenges, a sustainable and efficient solution was needed to optimize resource allocation, enhance soil durability, and boost site productivity.
حل
MetaFLO applied 0.037% of SoilTech biopolymer to a 500x12x0.2m3 track to demonstrate the technology’s potential for road stabilization. After being diluted directly in a water truck and applied to the track, SoilTech binds with the soil to form a hydrogel, and improves the soil’s mechanical properties after it cures. The treated soil exhibited increased mass density, better compaction, enhanced layer stabilization, and improved impermeability.
قبل وبعد
Outcome
✓ COST SAVINGS
On top of being environmentally friendly, SoilTech’s fast-acting soil stabilization reduced fuel consumption and polluting gas emissions by 25%, and saved the client 3 hours of labor—resulting in a total cost savings of 20% compared to traditional methods.
✓ WATER SAVINGS
Using SoilTech instead of traditional subgrade regularization methods saved a total of 80,000 liters of water throughout the project, reducing total water consumption by 33% and avoiding excessive water usage.
✓ ROAD QUALITY
24 hours after curing, particle cohesion in the soil was enhanced, compaction was improved, and impermeability was increased, leading to a more durable, safe and resilient road surface.